On May 30th, after the last truss’ installation, the installation of Xi’an Silk Road International Conference Center is finished. The total amount of steel structure is 66,000 tons, 7 times of Eiffel Tower, and it is only 90 days from start to finish installation, this is one of the advantages of steel structure buildings. Regardless of the difference between different projects, it only uses one-quarter of the installation time of Bird’s Nest Stadium and National Conference and Exhibition Center (Shanghai). The amount of Bird’s Nest Stadium is 50,000 tons, and it uses 300 days to finish the installation. The National Conference and Exhibition Center use 90,000 tons of steel, 330days. 2100 tons of steel members were installed each day, it is really fast. If you need a building urgently, then you should consider the steel structure, get in touch with us, China PEB.

 

The last beam of the steel structure conference center
The last beam of the steel structure conference center

Why can the installation so fast? It is because that the technical department take all the conditions into consideration in advance. At the beginning of the detailed design, they use BIM software to proceed with the detailed design, 3D solid modeling the structural components and the joints, find and solve the issues that may affect the installation. Analyse and calculate the whole steel structure model, divide the structure members reasonably, find the best hoist point. After their hard work, the installation was done smoothly.

All the steel parts, columns, beams, girder, purlin were produced in the steel structure workshop, the advanced production line, management during the lifetime of steel parts, producing every day as the design and follow the schedule, each member can be traced, ensure the production accuracy and quality stability. Every steel member is marked with letter and number, it shows in the installation map where it should be. The workers at the site will put the columns and beams at the right point following the installation drawing, no need to do other works, just put them in the spot and fasten the screws, then all is done, so it only needs one-third of the time of traditional construction. At the same time, Steel Structure Prefab buildings need less work field, less water, less material, less installation time, most of the members and components are produced in the steel structure factory (China PEB), reduced the noise, waste water, waste material and other pollution.

The last beam of the steel structure conference center

Contact China PEB, if you need some help of steel structure buildings, steel structure workshop, steel structure warehouse, steel structure shed, steel structure hangar, even steel villa, prefab house, and some other buildings have steel structure, you can let us know, we could help definitely.